FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (2024)

FMEA RPN has widely known as a Risk Priority Number (indicator) in an FMEA. But how to calculate it quickly and evaluate the FMEA RPN effectively? Let’s deep dive in!

1. Risk Priority Number definition

Risk Priority Number is a numerical assessment of the risk priority level of a failure mode/failure cause in an FMEA analysis. It helps the responsible team/individual prioritize risks and decide on the corrective actions.

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (1)

2. How to calculate the Risk Priority Number?

FMEA RPN is calculated by multiplying Severity (S), Occurrence (O) Or Probability (P), and Detection (D) indexes. Severity, Occurrence, and Detection indexes are derived from the failure mode and effects analysis:

Risk Priority Number = Severity x Occurrence x Detection
Severity: The severity of the failure mode is rated on a scale from 1 to 10. A high severity rating indicates severe risk.
Occurrence (or Probability): The potential of failure occurrence is rated on a scale from 1 to 10. A high occurrence rating reflects high failure occurrence potential.
Detection: The capability of failure detection is rated on a scale from 1 to 10. A high detection rating reflects low detection capability.

For example: from the Process FMEA of a painting process, the RPN is 120 for the failure mode of foreign body in the painting layer.

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (2)

Two options for calculating RPN in an FMEA worksheet

Method 1: Use the Excel formula. Because of the structure of the FMEA worksheet, the Severity cell is not linked one to one with the Occurrence and Detection cell, and the RPN formula needs to be created manually one by one.

Method 2: Use FMEA Studio Add-in inside Excel: Create a column with RPN column type inside Column Properties. RPN will be calculated automatically within a second for the whole FMEA worksheet. More detail about this feature are here.

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (3)

RPN is not the only risk assessment number used with FMEA. Some companies use other indexes to assess risks, such as the Critical Number (CN) or Severity-Occurrence-Detection (SOD). However, they are rarely used.

2.1 Critical Number (CN)

Some companies find it difficult to decide on a detection ranking. Therefore, they do not use detection (D) in their calculation of the RPN to avoid arguments regarding the detection ranking.

Critical Number (CN) = Severity (S) x Occurrence (O)

Quickly create CN for an FMEA worksheet: Insert a new column and set its data type as Critical Number

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (4)

2.2 SOD

The FMEA RPN does not cover all the numbers from 1 to 1000. Therefore, some companies use the numerical value of SOD. In this case, the ratings of S, O, and D range from 0 to 9 (not from 1 to 10).

SOD = 100 x S + 10 x O + D

Consider the following example.
[table id=2 /]

Although Failure Mode 1 has a higher SOD than Failure Mode 2, it has lower risk because its potential for occurrence is small, and the possibility of detection is high (if it happens).

Thus, the disadvantage of SOD is that severity has a more critical role than Occurrence and Detection in the SOD equation.

3. How to evaluate Risk Priority Number?

The RPN can be used to prioritize high-risk issues and determine the requirement for corrective action. After calculation, most companies prioritize risks from the highest to the lowest RPN.

The team can use the Risk Priority Number to prioritize and reduce risks in the two following methods:

3.1 FMEA RPN Threshold

Many organizations use an RPN limit to determine which failure mode requires corrective action and which risks are acceptable. The RPN threshold is easy to use.

However, using an RPN threshold may cause team members to spend excessive time trying to reduce the Detection, Occurrence, and Severity rankings for lowering the RPN. This situation sometimes places the organization and its customers in danger.

To apply the RPN threshold for an Excel FMEA worksheet, you can use Conditional Formatting or simply apply Threshold evaluation for Risk Priority Setting in FMEA Studio Add-in.

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (5)

3.2 Top RPNs

The other organizations may address the corrective action for the top failure modes/failures causes by Risk Priority Number. After that, the team will work with other top RPNs to continuously improve the process. This loop will continue until the quality target is met.

To apply the Top RPNs for an Excel FMEA worksheet. Similar to RPN Thresholds, you can use Conditional Formatting or simply apply Threshold evaluation for Risk Priority Setting in FMEA Studio Add-in.

4. Risk Priority Number’s disadvantage

The two ways above are based only on the comparison between the RPN of failure modes. The comparison based on the RPN may not reflect the actual risk. A high RPN failure does not necessarily indicate a high risk for the process or product. Moreover, two failure modes with the same RPN value may not have the same risk level.

In the following example from the automotive industry, Failure Mode 1 should be provided a higher priority than Failure Mode 2 although they have the same RPN value because it has a higher Severity value.
[table id=3 /]

However, because they have the same RPN value, an inappropriate action plan for critical failure may be selected. For this reason, the RPN should not be the only index used to evaluate the risk of each failure mode. The team should also use Severity, Occurrence, and Detection to prioritize risks.

5. How to evaluate the Risk Priority Number effectively?

5.1 Risk evaluation using the FMEA RPN with the consideration of the S, O, and D rankings

Along with RPN, the team should consider the S, O, and D rankings for prioritizing risks one by one through team discussion. However, the team will be overloaded if there are too many failure modes in the FMEA.

Moreover, teams can go through unending arguments to determine which failure requires corrective action.

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (6)

Conduct FMEA faster and easier with Excel

Compatible with AIAG/VDA FMEA Handbook

Download FMEA Studio

Go to FMEA Studio

5.2 Risk Matrix (Priority Matrix)

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (7)

The team can combine the criteria for the RPN and Severity, Occurrence, and Detection rankings by using a matrix. The following is an example of a risk matrix for the RPN and Severity ranking.

The following example of a risk matrix includes a combination of severity and occurrence.

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (8)


Color indicator:
• Red: must eliminate the risk or reduce its level.
• Yellow: should eliminate the risk or reduce its level but not mandatory.
• Green: Acceptable risk.

Note:
The team can use a three-dimensional matrix of Severity, Occurrence, and Detection. However, this type of risk matrix is complicated to use without an FMEA software like FMEA Studio.

The organizations can create a matrix depending on their process and available resources. However, the team should apply the criteria consistently.

6. Conclusion

Using the RPN in FMEA is the most common and convenient method of evaluating risk because the FMEA RPN is easy to understand, whereas the entire FMEA methodology is complicated.

However, using only the RPN to determine the failure mode that requires corrective action can cause severe quality problems in an organization.

Companies that wish to avoid the limitations of the RPN should evaluate risk with a combination of indices, such as Severity, Occurrence, and Detection.

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (9)

Conduct FMEA faster and easier with Excel

Compatible with AIAG/VDA FMEA Handbook

Download FMEA Studio

Go to FMEA Studio

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem (2024)

FAQs

FMEA RPN - Risk Priority Number. How to Calculate and Evaluate? | IQASystem? ›

Risk Priority Number

How to calculate risk priority number RPN? ›

In the third step, the three factors of severity, occurrence, and detectability are multiplied together to calculate the so-called risk priority number (RPN): RPN = S × O × D.

How to evaluate RPN in FMEA? ›

RPN was calculated the severity of event (S), the probability of occurrence (O) and probability of detection (D) according to the following formula: RPN = S × O × D. The RPN value for each failure ranges between 1 and 1000.

How is the risk priority number determined in a FMEA? ›

After the ratings have been assigned, the RPN for each issue is calculated by multiplying Severity x Occurrence x Detection. The RPN value for each potential problem can then be used to compare the issues identified within the analysis.

How to calculate action priority in FMEA? ›

The AP values are determined based on the values of the Severity, Occurrence, and Detection fields. The AP Revised values are determined based on the values of the Revised Severity, Revised Occurrence, and Revised Detection fields.

What are the three 3 components of a risk priority number RPN )? ›

Risk Priority Number (RPN) is the most frequently-adopted method in risk evaluation. In this method, three factors, Occurrence (O), Detection (D), and Severity (S), are used to test failure risks, evaluate the seriousness of failures, and determine the priority of settlement.

What factors are necessary to calculate a risk priority numbering? ›

Function: It helps prioritize risks by considering three key factors:
  • Severity (S): The seriousness of the consequences if the failure occurs. ...
  • Occurrence (O): The likelihood of the failure happening. ...
  • Detection (D): The probability that the failure will be identified before it causes a problem.
Mar 26, 2024

What is ideal RPN in FMEA? ›

Since each of the three relative ranking scales ranges from 1 to 10, the RPN will always be between 1 and 1000. The higher the RPN, the higher the relative risk. The RPN gives us an excellent tool to prioritize focused improvement efforts.

How to assess risk using FMEA? ›

The FMEA process begins by identifying all possible failure modes of a product or process. The second step is to determine the possible causes and resulting effects of those potential failures. You then assess the risk level associated with each of the failure modes based on a set of established criteria.

What is RPN in calculators? ›

Reverse polish notation, or RPN, is one of the three commonly used calculation notations. The other two are polish notation and infix notation. The latter, infix notation, is the one most commonly used across the world and is probably the form of notation that is most familiar to readers.

How do I reduce my risk priority number? ›

By reducing the severity, occurrence, or detection ratings of the failure modes, you can lower their RPNs and improve the quality and reliability of your process, product, or system.

How do you decide which risks should be given the highest priority? ›

With the Risk Impact/Probability Chart, you map out each risk – and its position determines its priority. High-probability/high-impact risks are the most critical, and you should put a great deal of effort into managing these.

What RPN number requires action? ›

By rule of thumb, any RPN value exceeding 80 requires a corrective action. The corrective action ideally leads to a lower RPN number.

How do you determine priority for action? ›

Prioritization involves determining the relative importance or urgency of each goal among a set of high-priority items. To achieve this, we evaluate each item against specific criteria or factors and consider the potential consequences of not completing each task within the given time frame.

How to decide severity in FMEA? ›

Severity is usually rated on a scale from 1 to 10, where 1 is insignificant and 10 is catastrophic. If a failure mode has more than one effect, write on the FMEA table only the highest severity rating for that failure mode. For each failure mode, determine all the potential root causes.

What is the formula for calculating risk level? ›

Risk is the combination of the probability of an event and its consequence. In general, this can be explained as: Risk = Likelihood × Impact.

How is risk assessment rating and priority calculated? ›

Risk scores are determined by multiplying the likelihood and consequence scores. The formula is Risk Level = Probability x Impact or Risk = Likelihood x Severity. The resulting score corresponds to a risk rating, often categorized as low, moderate, high, or extreme.

How to calculate risk assessment score? ›

Probability * highest impact

Probability x highest impact: this is a very common qualitative risk scoring calculation in which the highest impact score for all of the impact is used to calculate the risk score. For example, if you had a risk that had been assessed: Probability: Very High (5) Schedule: High (4)

References

Top Articles
Latest Posts
Article information

Author: Dong Thiel

Last Updated:

Views: 5488

Rating: 4.9 / 5 (59 voted)

Reviews: 90% of readers found this page helpful

Author information

Name: Dong Thiel

Birthday: 2001-07-14

Address: 2865 Kasha Unions, West Corrinne, AK 05708-1071

Phone: +3512198379449

Job: Design Planner

Hobby: Graffiti, Foreign language learning, Gambling, Metalworking, Rowing, Sculling, Sewing

Introduction: My name is Dong Thiel, I am a brainy, happy, tasty, lively, splendid, talented, cooperative person who loves writing and wants to share my knowledge and understanding with you.